Kingsley

Project: Domestic 10m swimming pool
Location: Kingsley, Cheshire
Cost: £225,000 + VAT
Contractor: AIS Contracts Ltd
Swimming Pool Contractor: KDT Swimming Pools Ltd
Structural Engineer: Peter Hewitt Associates

Feature Trusses: Dunscar Timber
Architects: Ian Banks & Julian Karczewski
Site Programme: 10 months
Service: Full RIBA Service Works Stage A – M
Contract: JCT Minor Works with Contractor Design
Project Status: Practical Completion 2010

 Description: The project brief was to create a free-standing single storey 10m residential ‘garden’ swimming pool and changing facilities – Planning Approved under Permitted Development. The pool and building is heated by an Air Source Heat Pump and electric power is subsidised by a photovoltaic array on the roof that utilised the Domestic Renewables Heat Incentive.

Scroll down for more images….